|
With energy consumption and energy cost on the rise, Oakland
University commissioned Cogen Designs, Inc. and Controlled
Performance, LLC to study the viability of a biomass
alternative to natural gas for its campus heating needs.
The study focused on the evaluation of potential waste wood
supplies, pricing and delivery options to the campus,
several wood boiler technologies, the ability to displace a
portion of the campus electric load, plant siting options,
and economic viability of the wood alternative.
It was determined that adequate urban wood
waste is available in a 14 county area around the campus to
reliably meet the fuel supply needs of this project. The
systems and modes of operation evaluated would consume
between 30,000 to 66,000 green tons of wood per year
depending upon the hours of operation and amount of
electrical power production. The 14 county area is
estimated to produce approximately 1.7 millions tons of
urban waste wood per year, with the majority going to a wood
fueled power plant in Flint, Canadian greenhouses, landscape
mulch, and landfills. This project would consume 1.5 to 3%
of the 14 county wood waste supply. These volumes do not
include agricultural residues or dedicated fuel crop
production, either of which could provide some or all of
this system’s fuel requirements in future years if they
prove economical.
Current pricing for urban waste is in the range of $25 - $30
per delivered ton, or roughly 1/3 the cost for the
equivalent fuel value of natural gas. A wood fuel cost of
$28 per ton was used in the economic proformas of this
study.
Both steam and HTHW boiler options were
evaluated. Stoker boilers were generally found to be less
expensive to build than fluidized bed systems. Combined
heat and power (CHP) systems could be used to take advantage
of surplus boiler capacity during the summer months, to
displace summer peak electrical power demands. These CHP
systems produced greater operating savings, although at the
expense of higher capital cost. None of the systems could
produce power that was lower in cost than purchased power
from Detroit Edison during Off Peak hours, although
substantial operating savings could result from peak
shaving.
Capital cost requirements varied from $14
million for a HTHW stoker boiler system to $27 million for a
fluidized bed high-pressure steam boiler with multiple steam
turbine electric generators. All scenarios included a new
boiler building, fuel storage, handling, and emissions
controls. First year Operating Savings varied from $1.5
million for a simple HTHW system to $1.7 million for a full
combined heat and power system operating in Peak Shaving
mode. The new operations for this new boiler plant included
five new operators. Stoker systems for HTHW production
generated the most attractive Returns on Investment (10 –
10.5%) and Simple Payback (9.4 – 9.7 years).
The greatest risk to project savings would be
from a decreasing natural gas costs, while decreases in
power cost or increases in wood cost had much smaller
impacts on project savings and returns. Capital cost risk
is greatest from the potential impact of site-related
issues, such as the resolution of drainage issues, high
temperature HTHW (HTHW) piping, electrical interconnects,
and truck delivery route infrastructure. More detailed
reviews of these civil and utility connection components
along with the beginning of the air permitting process are
the proposed next steps in the design process.
Overall, a wood-based boiler system has the
potential to produce significant operating savings for the
University, based on reasonable expectations for future fuel
and power prices.
|